Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 11, Issue 21;   May 25, 2011: Mitigating Risk Resistance Risk

Mitigating Risk Resistance Risk

by

Project managers are responsible for managing risks, but they're often stymied by insufficient resources. Here's a proposal for making risk management more effective at an organizational scale.
Flooding in Metarie, Louisiana, following Hurricane Katrina in 2005

Flooding in Metarie, Louisiana, following Hurricane Katrina. The photo was taken September 8, 2005. The Hurricane had made landfall nine days earlier, on August 29. The catastrophic scale of the damage was due, in part, to the scale of the storm, and, in part, to the manner in which the various governments involved managed risk and risk resistance. Dr. Walter Maestri, Emergency Management Consultant with DRC Group, was for over a decade the Director of Emergency Management for Jefferson Parish, Louisiana, of which Metarie is a part. Dr. Maestri held that position through the events associated with Hurricane Katrina. In a 2005 interview with the PBS program FRONTLINE, and on numerous other occasions including congressional testimony, Dr. Maestri told of funds promised but not allocated and mitigation plans revised or deferred. He is quoted as saying, "pay me now or pay me later. You're going to pay now, the estimates are more than $160 billion to rebuild this community. If you had pre-positioned all of the resources that needed to be here, if you had raised the levees or begun that process or looked at some of these other out-of-the-box ideas, it wouldn't have cost $160 billion, and we wouldn't have lost as much as we have." In response, government officials have argued that even if those plans had been executed, the catastrophe would not have been prevented, because the scale of the storm exceeded the design capacity of the mitigations. However, such a claim only indicts as inadequate the planned — but deferred — mitigations. Photo courtesy U.S. National Oceanic and Atmospheric Administration.

Risk resistance is the objection to all or part of a risk plan's content. Typically, objectors are project sponsors or senior managers. Typical objections are that the risks in question are fictitious, or that the mitigation plan is too expensive. Since the organizational power of the objectors generally exceeds that of the risk plan's authors, authors often simply eliminate or downgrade the items with which objectors disagree.

Although risks rarely materialize as projected, something similar often does. A classic example is the flooding of New Orleans in 2005. Concerns about such catastrophes trace back at least to the Flood Control Act of 1965, but the resources provided over the years for mitigating flood risk were most inadequate. The result of these mitigation downgrades is the disaster following Hurricane Katrina.

Downgrading risk plans — or their funding — doesn't downgrade the risk or make risk mitigation any cheaper. Instead, it opens gaps between risk plans and reality. That's how risk resistance creates risk. Here are four methods for addressing risk resistance risk.

Make risk plan revision traceable
Document risk plan revision in a Risk Plan Revision History — a section of the project plan that documents the downgrading of risk probability estimates and risk mitigation budgets.
Traceability facilitates corrective action when the organization is found unprepared for risks that do materialize. Record in the History the original risk plan elements, the reasoning supporting the modifications, and the dates of and parties to the downgrade decisions.
Retrospectively review gaps between risk plans and reality
After an unanticipated risk materializes, and its full impact on budget and schedule are known, review how it was addressed in the risk plan.
Was the risk anticipated in the final plan? If not, was it addressed in any earlier versions of the risk plan? Were earlier versions of the plan downgraded? Use the Risk Plan Revision History to answer these questions.
Measure risk response budgets and actuals
Keep accurate historical data measuring both the budget and actuals for risk response.
Managing risk more Document risk plan revision in
a Risk Plan Revision History
effectively requires narrowing the gap between risk plan budgets and risk response expenditures. Rarely do we have the necessary data available when we try to assess our risk performance. Start collecting it now.
Measure risk performance globally
Mitigating risk by taking actions that harm other projects can be expensive to the organization.
Some projects use political power to export the costs of their risk responses onto other projects. For example, reassigning people with rare skills — or holding onto them longer than planned — might aid one project, but it can harm others. To assign responsibility for these costs correctly, measure risk response costs across the entire organization, as opposed to per-project.

Objectors to risk plans, who often recognize the implications of the measures suggested here, might raise objections to implementing them. Begin advocacy or implementation only when you're prepared to meet those objections. Go to top Top  Next issue: Workplace Bullying and Workplace Conflict: I  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Your comments are welcome

Would you like to see your comments posted here? rbrenCFKlVARmidsjzQklner@ChacRQJyjoVRNVwxykNyoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Mess line, noon, Manzanar Relocation Center, California, 1943Remote Facilitation in Synchronous Contexts: II
Facilitators of synchronous distributed meetings — meetings that occur in real time, via telephone or video — encounter problems that facilitators of face-to-face meetings do not. Here's Part II of a little catalog of those problems, and some suggestions for addressing them.
Example of an unsecured driver-side floor mat trapping the accelerator pedal in a 2007 Toyota Lexus ES350Risk Management Risk: I
Risk Management Risk is the risk that a particular risk management plan is deficient. It's often overlooked, and therefore often unmitigated. We can reduce this risk by applying some simple procedures.
The Dalles of the St. Croix RiverThe Politics of the Critical Path: II
The Critical Path of a project is the sequence of dependent tasks that determine the earliest completion date of the effort. We don't usually consider tasks that are already complete, but they, too, can experience the unique politics of the critical path.
Eugene F. Kranz, flight director, at his console on May 30, 1965, in the Control Room in the Mission Control Center at HoustonDesign Errors and Group Biases
Design errors can cause unwanted outcomes, but they can also lead to welcome surprises. The causes of many design errors are fundamental attributes of the way groups function. Here is Part II of our exploration.
Rosemary Woods, President Richard Nixon's personal secretaryYet More Obstacles to Finding the Reasons Why
Part III of our catalog of obstacles encountered in retrospectives, when we try to uncover why we succeeded — or failed.

See also Project Management and Workplace Politics for more related articles.

Forthcoming issues of Point Lookout

Five almondsComing October 25: Workplace Memes
Some patterns of workplace society reduce organizational effectiveness in ways that often escape our notice. Here are five examples. Available here and by RSS on October 25.
Terminal 3 of Beijing Capital International AirportAnd on November 1: Risk Creep: I
Risk creep is a term that describes the insidious and unrecognized increase in risk that occurs despite our every effort to mitigate risk or avoid it altogether. What are the dominant sources of risk creep? Available here and by RSS on November 1.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenllvEPQQnPaitspOdner@ChacGYZTxaqnFeYJaCFPoCanyon.com or (617) 491-6289, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500 words in your inbox in one hour. License any article from this Web site. More info

Public seminars

Ten Project Management Fallacies: The Power of Avoiding Hazards
Most Ten Project Management Fallaciesof what we know about managing projects is useful and effective, but some of what we know "just ain't so." Identifying the fallacies of project management reduces risk and enhances your ability to complete projects successfully. Even more important, avoiding these traps can demonstrate the value and power of the project management profession in general, and your personal capabilities in particular. In this program we describe ten of these beliefs. There are almost certainly many more, but these ten are a good start. We'll explore the situations where these fallacies are most likely to expose projects to risk, and suggest techniques for avoiding them. Read more about this program. Here's a date for this program:

The Power Affect: How We Express Our Personal Power
Many The Power Affect: How We Express Personal Powerpeople who possess real organizational power have a characteristic demeanor. It's the way they project their presence. I call this the power affect. Some people — call them power pretenders — adopt the power affect well before they attain significant organizational power. Unfortunately for their colleagues, and for their organizations, power pretenders can attain organizational power out of proportion to their merit or abilities. Understanding the power affect is therefore important for anyone who aims to attain power, or anyone who works with power pretenders. Read more about this program.

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Twitter, or share a tweet Follow me at Google+ or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Workplace Politics Awareness Month KitIn October, increase awareness of workplace politics, and learn how to convert destructive politics into creative politics. Order the Workplace Politics Awareness Month Kit during October at the special price of USD 29.95 and save USD 10.00! Includes a copy of my tips book 303 Secrets of Workplace Politics which is a value!! ! Check it out!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.