Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 21, Issue 14;   April 7, 2021: Some Perils of Reverse Scheduling

Some Perils of Reverse Scheduling

by

Especially when time is tight, project sponsors sometimes ask their project managers to produce "reverse schedules." They want to know what would have to be done by when to complete their projects "on time." It's a risky process that produces aggressive schedules.
A reversed calendar page

A reversed calendar page for one month

Reverse scheduling is a common pattern that typically occurs in the course of negotiations between a project manager and the project's sponsor. The sponsor has a definite delivery date in mind, and naturally, prefers a low construction cost with minimum usage of precious resources. The pattern can emerge in a form such as this:

Sponsor: I need it by October 30.

Project manager: Then there isn't much time. I'll see what we can do.

Sponsor: Just bring me a schedule that gets it done by October 30. Work backwards from October 30 so we can see what we need to have and by when we need to have it.

At this point, the project manager convenes the leaders of the project team to explain the charge from the sponsor. They work out how they'll examine the problem, and that usually involves some project management software. There are some well-known traps associated with using conventional project management scheduling software to perform reverse scheduling. But this post is not about those traps.

Rather, in this post I explore the psychological traps associated with the whole idea of reverse scheduling. These traps cause the greater part of the trouble that results when the organization commits itself to unattainable objectives. And it is these traps that cause the people involved to believe that they are undertaking a project that they can actually complete successfully, when in fact, often, they cannot.

In what follows, I'll use the name Marguerite (M) to refer to the Project Manager (M), and the name Sean (S) to refer to the Project Sponsor (S).

Trying to design a project approach to deliver a result by a given date, working backwards from that date, exposes the project manager and the team to many risks, two of which lead planners to falsely assume that a workable schedule is even possible.

The false presumption of possibility

Believing There are psychological traps associated with
reverse scheduling that cause organizations
to commit to unattainable objectives
in the existence of a solution to the project-planning problem can be helpful in devising a workable plan. But believing doesn't make it so. The so-called "iron triangle of project management" is a metaphor that expresses the idea that we are not free to choose independently the attributes of a project and the product it creates. The attributes in question here are usually cited — rather tersely — as "scope, cost, schedule, and quality."

But the price of terseness is ambiguity, and in this instance ambiguity makes for some difficulty in understanding the applicability of the iron triangle metaphor. So let me take a moment to reduce the ambiguity. Scope refers to the capabilities of the project deliverables. In this context, a highly capable deliverable is good. Cost refers to the budget of the project. A low budget is good. Schedule refers to the delivery date of the project. An early date is good. And Quality refers to attributes of the deliverable, including ease of use, reliability, maintainability, and more. (Some include the quality of life of the project team in the definition of quality) In the iron triangle metaphor, the three sides of the triangle are scope, cost, and schedule. The angles between the sides (and/or in some formulations, the area of the triangle) represent the various quality attributes.

If we were designing a triangle, we would be free to choose, for example, the lengths of two of the sides and the angle between them. Having chosen them, the length of the third side is determined. There are other combinations that also work. You might recall from plane geometry that for triangles, we are free to choose side-side-side, side-angle-side, angle-side-angle, or angle-angle-side (see MathIsFun.com).

So, for example, in designing a project, how we constrain scope, schedule, and quality, can affect cost. Or we can choose all three of scope, cost, and schedule, but then quality is determined. And so on. This metaphor, like all metaphors, isn't precise. It communicates the idea that the four attributes of scope, cost, schedule, and quality are interrelated. We are not free to set them arbitrarily.

In the reverse scheduling scenario, Sean has specified scope and schedule explicitly. He hasn't said anything aloud about cost or quality, but for typical projects, every project manager knows that there are constraints on both cost and quality. And so there is a strong possibility that, in specifying scope and completion date, Sean has already implicitly over-determined the project-planning problem. It is therefore possible that a reverse scheduling problem violates the iron triangle of project management.

To avoid iron triangle violations, Sean must begin by acknowledging that there are constraints on cost and quality that he imposes implicitly. The other two elements of the iron triangle are schedule and scope. That leaves him with a choice of only two questions he can legitimately pose to Marguerite:

  • What part of X can you deliver by October 30?
  • How long would it take you to deliver X?

The first question leaves scope flexible; the second leaves schedule flexible. The reverse scheduling problem presumes that a solution exists after specifying bounds on scope, cost, schedule, and quality. Perhaps such a solution does exist, but in my experience with reverse scheduling, legitimate solutions are rare. Even if the planning team devises a plan that appears to meet the four targets for scope, cost, schedule, and quality, overruns of cost and schedule are likely; meeting scope and quality targets are unlikely.

How we get it wrong

Because project sponsors want what they want, the less experienced can (perhaps) be forgiven for posing over-determined problems to their project managers. But the more experienced should have learned about the iron triangle of project management. Many do learn; some seem not to.

More intriguing, though, is the question why project planners repeatedly accept the challenge of reverse scheduling a project. Many fail to anticipate the elevated risk of iron triangle violations in the reverse scheduling problem.

One possible explanation for this failure to anticipate might be provided by what are called priming effects. For a period of time after we're exposed to some form of stimulus, our responses to related stimuli are affected, often outside our awareness. The nature of the effect and period of time during which the effect is measurable depend on the kind of stimulus and the way it's presented. For example, before dining in a restaurant, visiting a bookstore and casually perusing a book about desserts can both elevate the probability that we might order dessert, and determine the actual dessert we select. These effects can occur completely outside our awareness.

When Sean (the project sponsor) tells Marguerite (the project manager) his desired delivery date for the project, that information can affect how Marguerite thinks about the project. Even if she believes she is remaining objective as she goes about calculating a schedule for the project, she has been primed to make judgments and interpretations that assume that the delivery date will be what Sean suggested. Outside her awareness, Marguerite begins to regard Sean's proposed date as a given, and she makes trade-offs and assumptions accordingly.

For example, project planners must make estimates of the time required to complete project tasks. As I've noted in a previous post, estimates are inherently syntheses of judgments and experience data. By compelling planners to achieve a specific target date, project sponsors create conditions in which priming effects can bias judgments. The bias isn't random. It consistently favors achieving the target date, which renders the estimates unrealistic.

Another source of bias, also a priming effect, cannot be traced to project sponsors. It is the knowledge that we cannot reschedule the past. That is, when project planners conduct their reverse scheduling exercise, they know the current calendar date. They know they cannot schedule a task to begin yesterday, last week, or last month. All tasks must begin in the future. And so, when after working backwards, they come to a point where they must estimate how long Task 31 will take, given that it must be complete, say, ten days from now, planners tend to estimate Task 31's duration to be ten days or fewer. If that estimate seems plainly ridiculous, then they try to push Task 31's completion date into the future, crowding any tasks that depend on Task 31. And so the waves of bias set off by knowing the current calendar date propagate forward into the future portions of the plan that have been so far defined.

But the biases triggered by knowing today's date are actually a little worse, because planners also know — or at least, have a guess — how long the reverse scheduling process might take. It might be days, or weeks for a complex project. Whatever is their guess, they know they cannot deliver to the sponsor a reverse schedule that shows tasks with start dates that are earlier than the date on which the deliver the new plan to the sponsor.

Last words

Thus, squeezed between Sean's target date and the date on which Marguerite delivers the reverse schedule to Sean, is a schedule for the project based on estimates biased just enough to appear to be feasible. The planners have focused so much of their effort on schedule that, typically, all considerations of effects on cost, scope, and quality have been set aside. The project might be completed on time, if the definition of complete has been expanded to include whatever the team can build, for whatever budget they have left, at whatever level of quality they can produce by October 30. Go to top Top  Next issue: What Micromanaging Is and Isn't  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Your comments are welcome

Would you like to see your comments posted here? rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

An air traffic controller using a display system at an Air Route Traffic Control CenterRemote Facilitation in Synchronous Contexts: I
Whoever facilitates your distributed meetings — whether a dedicated facilitator or the meeting chair — will discover quickly that remote facilitation presents special problems. Here's a little catalog of those problems, and some suggestions for addressing them.
Statue of Hermes with modern headTeamwork Myths: Formation
Much of the conventional wisdom about teams is in the form of over-generalized rules of thumb, or myths. In this first part of our survey of teamwork myths, we examine two myths about forming teams.
Captain Robert F. Scott and most of his team returning from the South PoleProject Improvisation and Risk Management
When reality trips up our project plans, we improvise or we replan. When we do, we create new risks and render our old risk plans obsolete. Here are some suggestions for managing risks when we improvise.
The Dalles of the St. Croix RiverThe Politics of the Critical Path: II
The Critical Path of a project is the sequence of dependent tasks that determine the earliest completion date of the effort. We don't usually consider tasks that are already complete, but they, too, can experience the unique politics of the critical path.
A working meeting with an auditorInternal Audits Without Pain
If adhering to established procedures is part of your job, you probably experience occasional audits. You can manage the pain of the experience by regarding audit preparation as part of the job. Because it is. Here are some tips for navigating audits.

See also Project Management and Cognitive Biases at Work for more related articles.

Forthcoming issues of Point Lookout

Three gears in a configuration that's inherently locked upComing April 24: Antipatterns for Time-Constrained Communication: 1
Knowing how to recognize just a few patterns that can lead to miscommunication can be helpful in reducing the incidence of problems. Here is Part 1 of a collection of communication antipatterns that arise in technical communication under time pressure. Available here and by RSS on April 24.
A dangerous curve in an icy roadAnd on May 1: Antipatterns for Time-Constrained Communication: 2
Recognizing just a few patterns that can lead to miscommunication can reduce the incidence of problems. Here is Part 2 of a collection of antipatterns that arise in technical communication under time pressure, emphasizing those that depend on content. Available here and by RSS on May 1.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.