Volume 25, Issue 34;   August 20, 2025: Earned Value and Goodhart's Law

Earned Value and Goodhart's Law

by

Earned Value Management, a widely used approach to project management, is most useful in contexts in which estimators are familiar with the Tasks, the Technologies, and the Teams. But even when they are familiar, Earned Value Management is vulnerable to the tactics of those who game the metrics.
Charles Goodhart delivers the keynote speech in the 2012 Long Finance Spring Conference

Charles Goodhart delivers the keynote speech in the 2012 Long Finance Spring Conference at Bank of America Merrill Lynch. The talk was entitled "Procyclicality of Financial Regulation: And how to deal with it." The event was hosted in partnership with Gresham College. This is a portion of an image (cc) Attribution-ShareAlike 3.0 Unported by Jamesfranklingresham, courtesy Wikimedia.

Earned Value Management (EVM) is an approach to project management that emphasizes the value produced to date, as compared to the value the project was planned to have produced, either to date or when completed. To those possessed of an analytical temperament, EVM is an appealing way to assess the state of a project, because it defines a variety of metrics related to progress. For some kinds of projects EVM works well. But EVM applied to some other projects can be misleading — even dangerous financially. In this post I examine how general awareness of the metrics of EVM makes projects vulnerable to "gaming" of those metrics.

A brief look at the Earned Value Method

The earned value method of managing a project entails monitoring a set of metrics defined in advance by the project team. Choices can vary, but typical metrics include:

  • Actual Cost (AC)
  • Actual Cost of Work Scheduled (ACWS)
  • Actual Cost of Work Performed (ACWP)
  • Planned Cost of Work Scheduled (PCWS)
  • Earned Value: Budget at Completion multiplied by Actual Percent Complete (EV)
  • Planned value: EV according to plan (PV)
  • Schedule Performance Index: (SPI = EV/PV)
  • Cost Performance Index: (CPI = EV/AC)
  • Budgeted Cost of Work Performed (BCWP)
  • Budgeted Cost of Work Scheduled (BCWS)

As might be evident, the effectiveness of the method depends critically on the fidelity of cost and schedule estimates. [Ogunjobi 2024] Consider, for example, PCWS (the Planned Cost of Work Scheduled). For this metric to have much utility, the estimators have to get both cost and schedule right. For this reason, EVM works best when estimates are accurate — when the Tasks, the Technologies, and the Teams are familiar.

But there are other phenomena that limit the effectiveness of EVM. One is known as Goodhart's Law.

How Goodhart's Law de-fangs Earned Value Management

Goodhart's For some kinds of projects EVM works well,
but EVM applied to some other projects can
be misleading — even dangerous financially
Law is an observation about managing by metrics. When we make known the metrics' goals, we risk collapse of the metrics, in part because people try to "game" the metrics by shading or manufacturing the data to produce the goal result. [Goodhart 1975] See "Goodhart's Law and Gaming the Metrics," Point Lookout for March 8, 2023.

Here's an example of Goodhart's law in action. A common approach to using earned value to manage a project involves monitoring the Cost Performance Index (CPI=EV/AC) to keep it above 1.0. A project in that configuration is spending $1.00 to produce $1.00 of value, and is said to be "cost-efficient." However, if a project team knows that its CPI is running below that level, the team might take steps to elevate its CPI by advancing a particular activity so that it occurs in the present measurement period. Not just any activity will do. By choosing one that happens to contribute significant earned value at significantly lower cost, the team can elevate its CPI. Similarly, rescheduling so as to push into the future an activity that will depress CPI (at the expense of a future period) also leads to a misrepresentation of project health.

Last words

Ordinarily, we track only those metrics that provide some gauge of progress. But there are other uses for metrics, such as detecting the gaming of metrics.

Project teams that intend to use EVM to manage the project would do well to monitor additional metrics that signal gaming the metrics. For the examples above, a signal might be rescheduling tasks that result in CPI near the goal value of 1.0. Rescheduling that involves more than one task, and which involves only tasks that contribute to decreasing CPI are worthy of special attention. Go to top Top  

52 Tips for Leaders of Project-Oriented OrganizationsAre your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!

Footnotes

Comprehensive list of all citations from all editions of Point Lookout
[Ogunjobi 2024]
Timi Ogunjobi. "How Earned Value Management (EVM) Can Fail to Accurately Predict Project Outcomes," LinkedIn Technology and Management, September 12, 2024, Available here. Retrieved 28 July 2025. Back
[Goodhart 1975]
Charles Goodhart. "Problems of Monetary Management: The U.K. Experience", in Courakis, Anthony S. (ed.), Inflation, Depression, and Economic Policy in the West. Totowa, New Jersey: Barnes and Noble Books (1981), p. 116. Order from Amazon.com. Back

Your comments are welcome

Would you like to see your comments posted here? rbrenaXXxGCwVgbgLZDuRner@ChacDjdMAATPdDNJnrSwoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Mountain fogSeeing Through the Fog
When projects founder, we're often shocked — we thought everything was moving along smoothly. Sometimes, with the benefit of hindsight, we can see that we had — or could have had — enough information to determine that trouble was ahead. Somehow it was obscured by fog. How can we get better at seeing through the fog?
Two U.S. Army soldiers use binoculars and a riflescope to watch for insurgentsScheduling as Risk Management
When we schedule a complex project, we balance logical order, resource constraints, and even politics. Here are some techniques for using scheduling to manage risk and reduce costs.
Rick Piltz, former senior associate in the U.S. Climate Change Science ProgramTen Approaches to Managing Project Risks: I
Risk management usually entails coping with losses if they do occur. Here's Part I of a concise summary of the options for managing risk.
Phoenix caissons being towed to form a Mulberry harbor off Normandy, June 1944Ten Approaches to Managing Project Risks: III
Project risk management strategies are numerous, but these ten strategies are among the most common. Here are the last three of the ten strategies in this little catalog.
A fly caught in a carnivorous plant known as a venus flytrap (Dionaea muscipula)Seven Planning Pitfalls: I
Whether in war or in projects, plans rarely work out as, umm well, as planned. In part, this is due to our limited ability to foretell the future, or to know what we don't know. But some of the problem arises from the way we think. And if we understand this we can make better plans.

See also Project Management for more related articles.

Forthcoming issues of Point Lookout

A meeting of a small team working to resolve a serious matterComing August 27: Contributions in Team Meetings: Content
Most meetings are structured around a linear agenda, if they are structured at all. But the order of the agenda might not be the order that optimizes productivity. This first post in a series about contributions to meetings considers alternative frameworks for structuring team meetings. Available here and by RSS on August 27.
Photo of Jack Webb as Sergeant Joe Friday from the television series DragnetAnd on September 3: Contributions in Team Meetings: Advocating
An agenda in the form of an ordered list of topics might not provide an appropriate framework for a given meeting. For example, if A depends on B, and B depends on A, we must find a way to discuss A and B together in some orderly fashion. Here are some alternatives to linear, ordered agendas. Available here and by RSS on September 3.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenaXXxGCwVgbgLZDuRner@ChacDjdMAATPdDNJnrSwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Bluesky, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.