Project plans usually include estimates of costs and schedules in addition to plans for work to be done, and the order of doing that work. Sometimes we fail to complete all the work we had in mind; sometimes we find we cannot do some work we wanted to do; sometimes we discover additional work we needed to do. But overall, the work actually done in a project does roughly approximate the work that was planned. Not so for cost and schedule. Cost and schedule can differ from projections by double, triple, and more, even when we make allowances for differences between work planned and work actually done.
In a 1977 report, Daniel Kahneman and Amos Tversky identify a particular cognitive bias, the planning fallacy, which afflicts planners. [Kahneman 1977] [Kahneman 1979] They discuss two types of information used by planners. Singular information is specific to the project at hand; distributional information is drawn from similar past efforts. The planning fallacy is the tendency of planners to pay too little attention to distributional information and too much attention to singular information, even when the singular information is scanty or questionable. Planners tend to underestimate cost and schedule by failing to harvest lessons from the distributional information, which is inherently more diverse and reliable than singular information.
But even when planners attend to distributional information, two forms of self-serving considerations can lead planners to make estimates that cannot be met. Here's how.
- Self-serving bias
- Choosing local experts is a common pattern for designating people to make estimates of cost and schedule. Usually the experts designated tend to be people who've done similar work in the past, and sometimes they must assess their own past work. When estimators must evaluate their own work, they have a conflict of interest that can compromise objectivity as a result of a cognitive bias known as self-serving bias. [Campbell 1999] Self-serving bias causes us to perceive ourselves more positively than objective judgment warrants. We tend to attribute successes to our own talents and decisions, and attribute failures to external factors.
- When the The work actually done in a
project does roughly approximate
the work that was planned.
Not so for cost and schedule.estimators designated for a project were themselves involved in the past efforts they're evaluating for estimation purposes — what Kahneman and Tversky call distributional information — self-serving bias tends to lead them to biased conclusions, which they then use to make projections for the project whose cost and schedule they're estimating. - Organizational politics
- From the perspective of objective estimation based on balanced assessment of distributional and singular information, organizational politics can make a bad situation even worse. Estimators who are evaluating past efforts in which they played roles can use their evaluations as tools of what psychologists call impression management — to make themselves look good. They can thus enhance their own prospects for advancement. [Drory 2006] In this way, politics can limit the willingness of estimators to faithfully represent sources of successes and failures in past efforts. In effect, to gain political advantage, estimators tend to attribute too much of the reason for past successes to their own actions, and too much of the reason for past failures to external factors or to the actions of others, especially political rivals.
The distortions that result from the planning fallacy, from self-serving bias, and from organizational politics can reduce the chances that estimators will produce reliable results. When that happens, cost overruns and schedule delays become more likely. Top Next Issue
Is every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info
Footnotes
Your comments are welcome
Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
- Why Scope Expands: II
- The scope of an effort underway tends to expand over time. Why do scopes not contract just as often?
One cause might be cognitive biases that make us more receptive to expansion than contraction.
- Team Risks
- Working in teams is necessary in most modern collaborations, but teamwork does carry risks. Here are
some risks worth mitigating.
- Ten Approaches to Managing Project Risks: II
- Managing risk entails coping with unwanted events that might or might not happen, and which can be costly
if they do happen. Here's Part II of our exploration of coping strategies for unwanted events.
- Some Risks of Short-Term Fixes
- When we encounter a problem at work, we must choose between short-term fixes (also known as workarounds)
and long-term solutions. Often we choose workarounds without appreciating the risks we're accepting
— until too late.
- The Reactive Rescheduling Cycle
- When the current schedule is no longer viable, we reschedule. But rescheduling is unlike devising a
schedule before work has begun. People know that we're "behind" and taking time to reschedule
only makes things worse. Political pressure doesn't help.
See also Project Management and Project Management for more related articles.
Forthcoming issues of Point Lookout
- Coming September 4: Beating the Layoffs: I
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily before the layoffs can carry significant advantages. Here are some that relate to self-esteem, financial anxiety, and future employment. Available here and by RSS on September 4.
- And on September 11: Beating the Layoffs: II
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily can carry advantages. Here are some advantages that relate to collegial relationships, future interviews, health, and severance packages. Available here and by RSS on September 11.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed