
An unfinished building, known as Szkieletor. Construction began in 1975, but stopped permanently in 1981 because of economic constraints and political unrest. Sometimes budgets aren't overrun. Sometimes they just run out. Image (cc) pl:Wikipedysta:Macieias courtesy Wikipedia.
Project plans usually include estimates of costs and schedules in addition to plans for work to be done, and the order of doing that work. Sometimes we fail to complete all the work we had in mind; sometimes we find we cannot do some work we wanted to do; sometimes we discover additional work we needed to do. But overall, the work actually done in a project does roughly approximate the work that was planned. Not so for cost and schedule. Cost and schedule can differ from projections by double, triple, and more, even when we make allowances for differences between work planned and work actually done.
In a 1977 report, Daniel Kahneman and Amos Tversky identify a particular cognitive bias, the planning fallacy, which afflicts planners. [Kahneman 1977] [Kahneman 1979] They discuss two types of information used by planners. Singular information is specific to the project at hand; distributional information is drawn from similar past efforts. The planning fallacy is the tendency of planners to pay too little attention to distributional information and too much attention to singular information, even when the singular information is scanty or questionable. Planners tend to underestimate cost and schedule by failing to harvest lessons from the distributional information, which is inherently more diverse and reliable than singular information.
But even when planners attend to distributional information, two forms of self-serving considerations can lead planners to make estimates that cannot be met. Here's how.
- Self-serving bias
- Choosing local experts is a common pattern for designating people to make estimates of cost and schedule. Usually the experts designated tend to be people who've done similar work in the past, and sometimes they must assess their own past work. When estimators must evaluate their own work, they have a conflict of interest that can compromise objectivity as a result of a cognitive bias known as self-serving bias. [Campbell 1999] Self-serving bias causes us to perceive ourselves more positively than objective judgment warrants. We tend to attribute successes to our own talents and decisions, and attribute failures to external factors.
- When the The work actually done in a
project does roughly approximate
the work that was planned.
Not so for cost and schedule.estimators designated for a project were themselves involved in the past efforts they're evaluating for estimation purposes — what Kahneman and Tversky call distributional information — self-serving bias tends to lead them to biased conclusions, which they then use to make projections for the project whose cost and schedule they're estimating. - Organizational politics
- From the perspective of objective estimation based on balanced assessment of distributional and singular information, organizational politics can make a bad situation even worse. Estimators who are evaluating past efforts in which they played roles can use their evaluations as tools of what psychologists call impression management — to make themselves look good. They can thus enhance their own prospects for advancement. [Drory 2006] In this way, politics can limit the willingness of estimators to faithfully represent sources of successes and failures in past efforts. In effect, to gain political advantage, estimators tend to attribute too much of the reason for past successes to their own actions, and too much of the reason for past failures to external factors or to the actions of others, especially political rivals.
The distortions that result from the planning fallacy, from self-serving bias, and from organizational politics can reduce the chances that estimators will produce reliable results. When that happens, cost overruns and schedule delays become more likely. Top
Next Issue
Is every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info
Footnotes
Your comments are welcome
Would you like to see your comments posted here? rbrentSgXnAlNVWlhxNIJner@ChacAtZoEYrrmofzZnjPoCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and
found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
Restarting Projects
- When a project gets off track, we sometimes cancel it. But since canceling projects takes a lot of courage,
we look for ways to save them if we can. Often, things do turn out OK, and at other times they don't.
There's a third choice, between pressing on with a project and canceling it. We can restart.
Shining Some Light on "Going Dark"
- If you're a project manager, and a team member "goes dark" — disappears or refuses to
report how things are going — project risks escalate dramatically. Getting current status becomes
a top priority problem. What can you do?
The Risky Role of Hands-On Project Manager
- The hands-on project manager manages the project and performs some of the work, too. There are lots
of excellent hands-on project managers, but the job is inherently risky, and it's loaded with potential
conflicts of interest.
Power Distance and Teams
- One of the attributes of team cultures is something called ``Em''power distance``/Em'', which is a measure
of the overall comfort people have with inequality in the distribution of power. Power distance can
determine how well a team performs when executing high-risk projects.
Lessons Not Learned: I
- The planning fallacy is a cognitive bias that causes us to underestimate the cost and effort involved
in projects large and small. Mitigating its effects requires understanding how we go wrong when we plan
projects by referencing our own past experience.
See also Project Management and Project Management for more related articles.
Forthcoming issues of Point Lookout
Coming April 2: Mitigating the Trauma of Being Laid Off
- Trauma is an emotional response to horrible events — accidents, crimes, disasters, physical abuse, emotional abuse, gross injustices — and layoffs. Layoff trauma is real. Employers know how to execute layoffs with compassion, but some act out of cruelty. Know how to defend yourself. Available here and by RSS on April 2.
And on April 9: Defining Workplace Bullying
- When we set out to control the incidence of workplace bullying, problem number one is defining bullying behavior. We know much more about bullying in children than we do about adult bullying, and more about adult bullying than we know about workplace bullying. Available here and by RSS on April 9.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrentSgXnAlNVWlhxNIJner@ChacAtZoEYrrmofzZnjPoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick





Recommend this issue to a friend
Send an email message to a friend
rbrentSgXnAlNVWlhxNIJner@ChacAtZoEYrrmofzZnjPoCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed
