Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 4, Issue 16;   April 21, 2004: Scheduling as Risk Management

Scheduling as Risk Management

by

Last updated: August 8, 2018

When we schedule a complex project, we balance logical order, resource constraints, and even politics. Here are some techniques for using scheduling to manage risk and reduce costs.
Two U.S. Army soldiers use binoculars and a riflescope to watch for insurgents

Two U.S. Army soldiers use binoculars and a riflescope to watch for insurgents downrange as they conduct a combat patrol near the Syrian border in Iraq on March 6, 2006. Patrol is a variant of "reconnaissance in force." Photo courtesy U.S. Department of Defense.

Turning the car key in the door lock, Marian was relieved that they'd finally agreed to get out for lunch, because she wanted a change of scene for the conversation she and Kevin and James were about to have. The door locks all clicked open, and the three of them hopped in.

"Where to," she said.

Kevin answered from the back seat: "You have to ask?"

Marian looked up at Kevin in the rear-view mirror. "Just trying to give you an opportunity for input," she replied. At the end of the loop road, she turned left towards Mike's, where they always went for lunch when projects were in trouble.

James began immediately. "I wish we'd found out about the Georgetown products before we did the Pyramid modules — we wouldn't be here now. But how could we have known?"

Kevin, of course, had the answer. "They could've told us," he said dryly. Marian and James laughed weakly.

"Yeah, there is that," Marian said. "But they've done this to us before. You'd think we would have learned by now."

Projects are full
of surprises — that's
what makes
them projects
Indeed. Projects are full of surprises — that's what makes them projects. Still, we can reduce the incidence of surprises by cleverly sequencing the project's tasks. Here are some tips for using schedule to manage risk.

Avoid the logical-order trap
Some projects impose a logical order on task sequence. A building, for example, has to have its foundation in place before the first structural elements go up. But unless the laws of physics intervene, keep an open mind about the order of things.
Exploit leverage
Give preference to tasks that reduce costs, either because they spin off tools you can use, or because you can learn something valuable, or because they provide a morale boost.
Delay creating what you don't need
Building or designing something before it's needed creates constraints through commitment. Delaying preserves flexibility.
If you think something might be difficult, find out early
Schedule the solutions to unsolved problems so that bad news arrives early, when you have time to sort out alternate approaches, and before other elements impose constraints.
Use reconnaissance teams
Designate teams to perform reconnaissance in force, looking for traps before the main body of the project reaches them. Give these teams enough budget to run tests that reveal weaknesses before you've made major commitments.
Avoid resource optimization
Shortening the critical path by optimizing resource allocation is a risky strategy. Most development projects aren't predictable enough for this kind of fine-tuning.
Get comfortable with placeholders
We use placeholders when scheduling requires them, especially in the critical path. But building placeholders is a wonderful way to reconnoiter — to find out about trouble early. Use them more often.

You can do the same things when you read. Sometimes reading the end first gives you a useful mental framework for the beginning and middle. If you're doing that right now, I hope you enjoy reading the beginning and the middle of this article. Go to top Top  Next issue: Non-Workplace Politics  Next Issue

52 Tips for Leaders of Project-Oriented OrganizationsAre your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!

Your comments are welcome

Would you like to see your comments posted here? rbrenmhXARWRMUvVyOdHlner@ChacxgDmtwOKrxnripPCoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Shackleton, Scott and Wilson, of the British Antarctic Expedition 1902The Injured Teammate: II
You're a team lead, and one of the team members is suddenly very ill or has been severely injured. How do you handle it? Here are some suggestions for breaking the news to the team.
A section of the Rose Kennedy Greenway in Boston in 2008The Politics of the Critical Path: I
The Critical Path of a project or activity is the sequence of dependent tasks that determine the earliest completion date of the effort. If you're responsible for one of these tasks, you live in a unique political environment.
An A-10 Thunderbolt II over Afghanistan in 2011Down in the Weeds: I
When someone says, "I think we're down in the weeds," a common meaning is that we're focusing on inappropriate — and possibly irrelevant — details. How does this happen and what can we do about it?
Astronauts Musgrave and Hoffman install corrective optics during the Hubble Telescope's Service Mission 1How We Waste Time: I
Time is the one workplace resource that's evenly distributed. Everyone gets exactly the same share, but some use it more wisely than others. Here's Part I of a little catalog of ways we waste time.
The Leonard P. Zakim Bunker Hill BridgePlanning Disappointments
When we plan projects, we make estimates of total costs and expected delivery dates. Often these estimates are so wrong — in the wrong direction — that we might as well be planning disappointments. Why is this?

See also Project Management for more related articles.

Forthcoming issues of Point Lookout

A railroad switchComing April 8: The New Virtual Meeting: Digressions
The bane of meetings everywhere, even before the COVID-19 pandemic, has been digressions. But there are reasons to expect the incidence of digressions in meetings to increase now. What reasons could there be, and what can we do about digressions? Available here and by RSS on April 8.
Child's toys known as Chinese finger trapsAnd on April 15: Incompetence: Traps and Snares
Sometimes people judge as incompetent colleagues who are unprepared to carry out their responsibilities. Some of these "incompetents" are trapped or ensnared in incompetence, unable to acquire the ability to do their jobs. Available here and by RSS on April 15.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenmhXARWRMUvVyOdHlner@ChacxgDmtwOKrxnripPCoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500 words in your inbox in one hour. License any article from this Web site. More info

Public seminars

The Power Affect: How We Express Our Personal Power

Many The Power Affect: How We Express Personal Powerpeople who possess real organizational power have a characteristic demeanor. It's the way they project their presence. I call this the power affect. Some people — call them power pretenders — adopt the power affect well before they attain significant organizational power. Unfortunately for their colleagues, and for their organizations, power pretenders can attain organizational power out of proportion to their merit or abilities. Understanding the power affect is therefore important for anyone who aims to attain power, or anyone who works with power pretenders. Read more about this program.

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Twitter, or share a tweet Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
52 Tips for Leaders of Project-Oriented OrganizationsAre your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around.
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.
Comprehensive collection of all e-books and e-bookletsSave a bundle and even more important save time! Order the Combo Package and download all ebooks and tips books at once.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!