Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 11, Issue 21;   May 25, 2011: Mitigating Risk Resistance Risk

Mitigating Risk Resistance Risk

by

Project managers are responsible for managing risks, but they're often stymied by insufficient resources. Here's a proposal for making risk management more effective at an organizational scale.
Flooding in Metarie, Louisiana, following Hurricane Katrina in 2005

Flooding in Metarie, Louisiana, following Hurricane Katrina. The photo was taken September 8, 2005. The Hurricane had made landfall nine days earlier, on August 29. The catastrophic scale of the damage was due, in part, to the scale of the storm, and, in part, to the manner in which the various governments involved managed risk and risk resistance. Dr. Walter Maestri, Emergency Management Consultant with DRC Group, was for over a decade the Director of Emergency Management for Jefferson Parish, Louisiana, of which Metarie is a part. Dr. Maestri held that position through the events associated with Hurricane Katrina. In a 2005 interview with the PBS program FRONTLINE, and on numerous other occasions including congressional testimony, Dr. Maestri told of funds promised but not allocated and mitigation plans revised or deferred. He is quoted as saying, "pay me now or pay me later. You're going to pay now, the estimates are more than $160 billion to rebuild this community. If you had pre-positioned all of the resources that needed to be here, if you had raised the levees or begun that process or looked at some of these other out-of-the-box ideas, it wouldn't have cost $160 billion, and we wouldn't have lost as much as we have." In response, government officials have argued that even if those plans had been executed, the catastrophe would not have been prevented, because the scale of the storm exceeded the design capacity of the mitigations. However, such a claim only indicts as inadequate the planned — but deferred — mitigations. Photo courtesy U.S. National Oceanic and Atmospheric Administration.

Risk resistance is the objection to all or part of a risk plan's content. Typically, objectors are project sponsors or senior managers. Typical objections are that the risks in question are fictitious, or that the mitigation plan is too expensive. Since the organizational power of the objectors generally exceeds that of the risk plan's authors, authors often simply eliminate or downgrade the items with which objectors disagree.

Although risks rarely materialize as projected, something similar often does. A classic example is the flooding of New Orleans in 2005. Concerns about such catastrophes trace back at least to the Flood Control Act of 1965, but the resources provided over the years for mitigating flood risk were most inadequate. The result of these mitigation downgrades is the disaster following Hurricane Katrina.

Downgrading risk plans — or their funding — doesn't downgrade the risk or make risk mitigation any cheaper. Instead, it opens gaps between risk plans and reality. That's how risk resistance creates risk. Here are four methods for addressing risk resistance risk.

Make risk plan revision traceable
Document risk plan revision in a Risk Plan Revision History — a section of the project plan that documents the downgrading of risk probability estimates and risk mitigation budgets.
Traceability facilitates corrective action when the organization is found unprepared for risks that do materialize. Record in the History the original risk plan elements, the reasoning supporting the modifications, and the dates of and parties to the downgrade decisions.
Retrospectively review gaps between risk plans and reality
After an unanticipated risk materializes, and its full impact on budget and schedule are known, review how it was addressed in the risk plan.
Was the risk anticipated in the final plan? If not, was it addressed in any earlier versions of the risk plan? Were earlier versions of the plan downgraded? Use the Risk Plan Revision History to answer these questions.
Measure risk response budgets and actuals
Keep accurate historical data measuring both the budget and actuals for risk response.
Managing risk more Document risk plan revision in
a Risk Plan Revision History
effectively requires narrowing the gap between risk plan budgets and risk response expenditures. Rarely do we have the necessary data available when we try to assess our risk performance. Start collecting it now.
Measure risk performance globally
Mitigating risk by taking actions that harm other projects can be expensive to the organization.
Some projects use political power to export the costs of their risk responses onto other projects. For example, reassigning people with rare skills — or holding onto them longer than planned — might aid one project, but it can harm others. To assign responsibility for these costs correctly, measure risk response costs across the entire organization, as opposed to per-project.

Objectors to risk plans, who often recognize the implications of the measures suggested here, might raise objections to implementing them. Begin advocacy or implementation only when you're prepared to meet those objections. Go to top Top  Next issue: Workplace Bullying and Workplace Conflict: I  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Your comments are welcome

Would you like to see your comments posted here? rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Damage to the Interstate 10 Twin Bridge across Lake PontchartrainManaging Risk Revision
Prudent risk management begins by accepting the possibility that unpleasant events might actually happen. But when organizations try to achieve goals that are a bit out of reach, they're often tempted to stretch resources by revising or denying risks. Here's a tactic for managing risk revision.
The interior of an Apple store, location unknownPersonnel-Sensitive Risks: I
Some risks and the plans for managing them are personnel-sensitive in the sense that disclosure can harm the enterprise or its people. Since most risk management plans are available to a broad internal audience, personnel-sensitive risks cannot be managed in the customary way. Why not?
Dunlin flock at Nelson Lagoon, AlaskaNonlinear Work: Internal Interactions
In this part of our exploration of nonlinear work, we consider the effects of interactions between the internal elements of an effort, as distinguished from the effects of external changes. Many of the surprises we encounter in projects arise from internals.
The Great Wall of China near MutianyuScope Creep and Confirmation Bias
As we've seen, some cognitive biases can contribute to the incidence of scope creep in projects and other efforts. Confirmation bias, which causes us to prefer evidence that bolsters our preconceptions, is one of these.
A reversed calendar pageSome Perils of Reverse Scheduling
Especially when time is tight, project sponsors sometimes ask their project managers to produce "reverse schedules." They want to know what would have to be done by when to complete their projects "on time." It's a risky process that produces aggressive schedules.

See also Project Management and Workplace Politics for more related articles.

Forthcoming issues of Point Lookout

A close-up view of a chipseal road surfaceComing July 3: Additive bias…or Not: II
Additive bias is a cognitive bias that many believe contributes to bloat of commercial products. When we change products to make them more capable, additive bias might not play a role, because economic considerations sometimes favor additive approaches. Available here and by RSS on July 3.
The standard conception of delegationAnd on July 10: On Delegating Accountability: I
As the saying goes, "You can't delegate your own accountability." Despite wide knowledge of this aphorism, people try it from time to time, especially when overcome by the temptation of a high-risk decision. What can you delegate, and how can you do it? Available here and by RSS on July 10.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.