To manage risks properly, we must allocate resources to implement a risk management plan. Some resources must be allocated in advance of anticipated risk events, and some must be held in reserve "just in case."
Many organizations have difficulty allocating these resources, especially when resources are thin and risks haven't yet materialized. The temptation to hope that all will go well can lead some to attempt projects with insufficient reserves for risks. And it can lead others to deny that specific risks can ever occur.
For example, despite decades of widely accepted predictions, the U.S. government failed to provide adequate resources to New Orleans for hurricane-induced flood risk mitigation and planning.
In the project environment, at best, project managers or risk officers identify risks and propose resources to mitigate them. Project sponsors and organizational management then review these proposals for sufficiency and reasonableness. They negotiate with the project staff as necessary, and then they allocate appropriate resources for risk mitigation and management.
In many organizations, things rarely work that way. Organizations commit themselves to risk plans that amount to little more than naïve hopes and wishes for the best. How does this happen?
In some cases, the available resources cannot cover all identified risks unless everything breaks favorably. When someone identifies a risk that's expensive to manage, risk revision, exclusion, or denial enables those involved to commit to the effort despite resource shortages. When this happens, risks that do materialize can threaten the project — or worse, threaten the enterprise.
What can organizations do to manage risk revision?
One approach involves adding to the project plan an Appendix of Revised or Excluded Risks — risks that someone proposed, but which were edited before inclusion in the risk plan, or excluded altogether. For each revised risk, the appendix includes the original proposed risk, a revision history with dates, the arguments in favor of and against such revisions, and the names of all involved in each revision decision. The Appendix of Revised or Excluded Risks serves several purposes.
- Audit trail
- If the organization someday decides how particular risk types are to be addressed, the Appendix becomes a useful tool to help project teams bring their projects into compliance.
- Deterrence
- When available resources
can't cover all identified
risks, we sometimes
revise the risks - To whatever extent organizational politics or intimidation play any role in risk revision or exclusion, the knowledge that revision decisions will be recorded in the Appendix might deter some intimidators or some who abuse political power to achieve their ends.
- Support for organizational learning
- The Appendix could provide useful data for project retrospectives, or even earlier, if trouble does appear during the project's execution.
If you think risk revision and denial aren't happening in your organization, you might want to add that observation to your Appendix of Revised or Excluded Risks. Top Next Issue
Projects never go quite as planned. We expect that, but we don't expect disaster. How can we get better at spotting disaster when there's still time to prevent it? How to Spot a Troubled Project Before the Trouble Starts is filled with tips for executives, senior managers, managers of project managers, and sponsors of projects in project-oriented organizations. It helps readers learn the subtle cues that indicate that a project is at risk for wreckage in time to do something about it. It's an ebook, but it's about 15% larger than "Who Moved My Cheese?" Just . Order Now! .
Your comments are welcome
Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
- The Injured Teammate: I
- You're a team lead, and one of the team members is very ill or has been severely injured. How do you
handle it? How do you break the news? What does the team need? What do you need?
- The Politics of the Critical Path: II
- The Critical Path of a project is the sequence of dependent tasks that determine the earliest completion
date of the effort. We don't usually consider tasks that are already complete, but they, too, can experience
the unique politics of the critical path.
- How to Get Out of Firefighting Mode: I
- When new problems pop up one after the other, we describe our response as "firefighting."
We move from fire to fire, putting out flames. How can we end the madness?
- Planning Disappointments
- When we plan projects, we make estimates of total costs and expected delivery dates. Often these estimates
are so wrong — in the wrong direction — that we might as well be planning disappointments.
Why is this?
- Project Procrastination
- Sometimes we delay dealing with one of a project's tasks because circumstances require it. At other
times, we're procrastinating — the delay makes us more comfortable or provides personal benefits.
Here are five causes of project procrastination.
See also Project Management and Project Management for more related articles.
Forthcoming issues of Point Lookout
- Coming December 11: White Water Rafting as a Metaphor for Group Development
- Tuckman's model of small group development, best known as "Forming-Storming-Norming-Performing," applies better to development of some groups than to others. We can use a metaphor to explore how the model applies to Storming in task-oriented work groups. Available here and by RSS on December 11.
- And on December 18: Subgrouping and Conway's Law
- When task-oriented work groups address complex tasks, they might form subgroups to address subtasks. The structure of the subgroups and the order in which they form depend on the structure of the group's task and the sequencing of the subtasks. Available here and by RSS on December 18.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed